When Jayanta Cheleng’s uncle needed urgent treatment in Dibrugarh, the last ferry had already gone. The family arranged a special crossing for ₹7,500. Recalling the episode to Scroll in April 2019, Cheleng pointed out that his cousins could afford it; other families might not. By then, the Bogibeel bridge had opened, giving the north bank a road to the hospitals across the Brahmaputra. [1]
The 4.94-kilometre crossing carries a double railway line and a three-lane road. Narendra Modi inaugurated it on 25 December 2018 and flagged off the first passenger train through the bridge, linking Dibrugarh and Dhemaji districts. For the railway, it was a new connection across a formidable river. For families seeking treatment, it removed a break in the journey at precisely the point where delay could matter most. [2] [3]
Twenty-one years on the books
Bogibeel was sanctioned in 1997–98. Work commenced in April 2002 under Atal Bihari Vajpayee’s government, according to the Railways’ completion account. It subsequently passed through the UPA years before being finished under Modi. The same account put the original sanction at ₹1,000 crore and the completion cost at approximately ₹5,820 crore. These are project figures, encompassing more than the visible bridge alone. [3]
A parliamentary reply from July 2014 provides a useful intermediate picture. The government said ₹3,041 crore had been spent through March that year. By the time of the reply, both guide bunds and several connecting rail sections were complete. Of the main bridge’s 42 well foundations, 36 were finished; 28 of 40 piers were complete, but only two of 41 girders had been launched. [4]
Those numbers show the difficulty of assigning the entire structure to a single administration. Much of the foundation and connecting infrastructure existed when the government changed, while major work remained above the river. The July reply targeted March 2017 for completion. The opening came in December 2018. [4] [2]
A shorter journey, a changed riverbank
The significance of the road became apparent quickly. In its April 2019 reporting, Scroll described the Lakhimpur–Dibrugarh drive as taking about three hours, against almost half a day previously when ferry waiting was included. This was a contemporary journey comparison, not a universal saving for every origin and destination. The interviews establish a practical improvement in access; they do not establish how many deaths the bridge prevented. [1]
Three days after inauguration, The Times of India found the old Bogibeel ferry ghat largely deserted. An Inland Water Transport employee told the newspaper that services at both the Bogibeel and Kareng Bali ghats had closed. Shops and eateries dependent on waiting passengers were shutting too. The benefits to travellers arrived alongside a sudden loss of customers for people at the ghats. [5]
One boatman interviewed there, Shankar Sahani, said he welcomed the bridge despite losing his work and would seek another livelihood. His response captured the complicated transition along the river: a crossing long awaited by its users had opened, and the people who had carried them across now had to find a place in the economy it created. [5]
Sources
- Bridging the Barak and the Brahmaputra: Will Assam’s newfound connectivity help the BJP?
- PM dedicates Bogibeel bridge to the nation; flags off first passenger train
- Initiatives & Achievements of Ministry of Railways in the year 2018
- Bogibeel Rail-Cum-Road Bridge Project Targeted for Completion by March 2017
- Bogibeel Bridge leaves bustling ferry ghat deserted