At the opening of its Sanand facility on 28 February 2026, Micron presented a first shipment of Indian-made memory modules to Dell Technologies for laptops made in India. The company said commercial production had begun; Narendra Modi inaugurated the facility the same day. A project announced in 2023 now had a named customer receiving its output. [1] [5]

Sanand’s role was specific. It took advanced DRAM and NAND wafers from Micron’s global manufacturing network and converted them into finished memory and storage products through assembly and testing. These are semiconductor-manufacturing operations, but they do not mean the memory circuitry on those wafers was fabricated at Sanand. [1]

India also had semiconductor capability before this project. The government’s Semi-Conductor Laboratory, reorganised under the Department of Space in 2006, operates a wafer-fabrication line at Mohali and provides design, packaging and testing services. Micron’s new commercial memory operation belonged to a different segment and scale of the industry; calling it India’s first semiconductor of any kind would erase that earlier work. [4]

A jointly financed factory

Micron’s June 2023 announcement committed up to $825 million over two phases. Union support was to cover 50% of project cost and Gujarat incentives another 20%, bringing combined company and government investment to up to $2.75 billion. [2]

The larger amount described a joint project, not Micron’s investment alone. These were funding commitments, not certified expenditure. Public support helped finance the factory; Micron brought its technology and commercial network. [2]

Cabinet approval came in June 2023 and groundbreaking followed in September, according to a contemporary parliamentary update. The original company announcement expected the first phase to start becoming operational in late 2024. The confirmed commercial-production milestone arrived in February 2026, later than that expectation. Pilot activity and equipment installation in between should not be substituted for the commercial start. [2] [3] [5]

Production begins, scale builds

The early employment estimates were also forward-looking. The December 2023 government update anticipated up to 5,000 direct and 15,000 indirect jobs over five years. Those were prospective opportunities, rather than the number employed at Sanand when the factory opened. [3]

Micron forecast assembly and testing of tens of millions of chips during 2026, rising to hundreds of millions in 2027. Its stated first-phase cleanroom area of more than 500,000 square feet applied to full ramp-up. These descriptions did not establish immediate operation at the planned scale. [1]

By September, chief executive Sanjay Mehrotra told SEMICON India that finished DRAM and NAND products were leaving Gujarat for customers worldwide. He also described engineering work in Bengaluru and Hyderabad that had preceded the factory, and more than 7,000 employees across India—a broader workforce than Sanand’s. The government’s conference account separately recorded his confirmation that commercial production was live. [6] [7]

Sources

  1. Micron celebrates opening of Sanand assembly and test facility
  2. Micron announces assembly and test investment in India
  3. Micron’s semiconductor project at Sanand — parliamentary update
  4. Introduction to Semi-Conductor Laboratory
  5. Prime Minister inaugurates Micron ATMP facility in Sanand
  6. Micron CEO describes Sanand shipments and planned scale-up at SEMICON India
  7. SEMICON India 2026 — government account of industry statements